7 T/H Cat Litter Factory in Japan

Cat litter production equipment reference

Bentonite and tofu litter do not compete on the same production specification. Clay granules need controlled swelling, clump strength and resistance to dusting. Fibre-and-starch pellets need uniform diameter, reliable binding and stable moisture during storage. For this customer, the useful starting point was a pair of product specifications that could be checked after bagging, rather than a single granulator rating.

The incoming forms also set the plant boundary. This design uses purchased bentonite powder, dry starch and finely prepared soybean fibre. It avoids an ore-crushing plant and a wet-okara dewatering section. RICHI also supplies feed-processing lines for suitable dry soybean coproducts; those require a separate formulation and hygiene assessment and are outside this litter project’s output.

The customer is a pet-products company serving the Japanese market. Its cat litter production line project combines two independent material routes within an existing four-storey building. The reference production split is 4.5 T/H of finished bentonite litter and 2.5 T/H of finished tofu litter. Each figure is measured after drying, cooling and screening, so saleable tonnage is kept separate from the heavier wet feed entering the machines.

The project budget is carried in the investment card below. It is a total-project planning figure, with the purchase scope to be agreed before an equipment order. The operating calendar provides 300 days and two eight-hour shifts per day, or 4,800 scheduled hours. Fifteen employees cover the two shifts and shared support. The reference duties require about 4,444 effective hours on the mineral line and 4,000 on the tofu line.

capacity

investment

location

project type

The building has a 2,200 m² footprint and 8,800 m² of gross floor area over four storeys. Its large upper-floor area does not make every location suitable for bulk solids or vibrating machinery. The two-floor cat litter processing layout puts dense mineral stock, both dryers and dispatch at ground level; the tofu mixing and forming room occupies a segregated part of the second floor.

Upper floors are assigned mainly to light packaging, maintenance stores, staff facilities and reserved space. Heavy starch and fibre stocks stay in the ground-floor receiving zone. Structural review covers static stock loads, granulator vibration, machinery lifting and the dryer-support arrangement. The building programme has no canteen or dormitory; vehicle access and external utility positions belong to the surrounding industrial site plan.

Floor / footprintReference allocationInstallation condition
Ground / 2,200 m²700 m² mineral process; 400 m² tofu drying; 450 m² raw receiving; 350 m² finished stock; 180 m² utilities; 120 m² circulationHeavy ingredients and both dryers at ground level; separate enclosed product routes
Second / 2,200 m²700 m² tofu forming; 200 m² controlled buffers; 100 m² quality room; 200 m² access; 1,000 m² reserve4–5 m clear equipment height is a design requirement; structural and vibration review before installation
Third / 2,200 m²300 m² maintenance stores; 400 m² light packaging; 150 m² services; 200 m² access; 1,150 m² reserveApprove individual rack loads; no unassessed bulk-ingredient stock
Fourth / 2,200 m²500 m² light packaging; 150 m² staff rooms; 200 m² access; 1,350 m² reserveKeep major machinery and dense stock on approved lower-level supports
Building and site interfaces8,800 m² gross floor area; 2,200 m² building footprintExternal access, gas equipment and exhaust positions require the industrial-site plan; no canteen or dormitory

For the cat litter factory in Japan, the cat litter making machine reference selection uses one forming machine per material route. A custom disc pelletizer makes rounded bentonite granules; one MSZLH320 with a 37 kW main motor forms the tofu pellets. The equipment schedule below sizes the paired dryers, screens, conveying and packing duties around those machines. Final selection follows trials on the buyer’s actual clay and fibre-starch blend.

Equipment / quantityReference selectionMatched process duty
Bentonite forming / 1Custom 3 m disc pelletizer; 11 kW drive; continuous pre-wetting mixer 15 kWEngineering starting selection for 6 T/H wet-feed duty; prove granule quality and recycle rate by trial
Tofu forming / 1MSZLH320; main motor 37 kW; feeder 1.5 kW; conditioner 4 kWPublished nominal 3–4 T/H; design wet feed about 2,933 kg/h for 2.5 T/H net at 2 mm diameter
Tofu mixing / 1SLHSJ1A; 7.5 kW; 500 kg total wet charge; eight-minute total cycle3.5 T/H conservative working duty after handling allowance; water and returns included in batch weight
Ingredient preparation / 122 kW fibre trim grinder with a bypassOnly for incoming dry fibre failing the agreed size specification; no wet-residue dryer in this boundary
Mineral belt dryer / 1Multi-pass gas-heated unit; 750 kg/h water-evaporation design; 1 MW fuel input; fans and belt drives 30 kWAbout 560 kg/h evaporation at the reference mineral output
Tofu belt dryer / 1mesh Belt dryer with indirect gas-fired air heating; 500 kg/h evaporation; 750 kW fuel input; fans and drives 22 kWAbout 383 kg/h evaporation; separate clean-air circuit for the organic product
Cooling and screening / 2 routesMineral cooler 11 kW and screen 3 kW; tofu cooler 7.5 kW and screen 1.5 kWMineral route 6 T/H and tofu route 3 T/H dry handling; defined fines and oversize cuts
Automatic packing / 2One product-dedicated system per route; 11 kW electrical allowance eachAt 5 kg/bag: mineral 15 bags/min and tofu 10 bags/min demonstrated net, including sealing; bag-volume trial required
Dust and transfer systemsSeparate collectors: mineral 15 kW, organic 11 kW; conveyors and feeders sized by bulk densityOrganic protection follows material testing; dry return paths stay separate
Shared servicesGoods lift 11 kW; air compressor 15 kW; water metering pumps 2 kW; lighting and control allowance 12 kWReference total connected electrical load 302 kW; 500 kVA supply at 0.85 power factor gives 425 kW capacity

The reference material account uses accepted fresh ingredients at 10% moisture and packed litter at 8%, all on a wet basis. Fresh ingredients exclude rejected incoming deliveries. Clean screening returns equal 2% of saleable output and stay inside their own line. The base formulation is unscented. Fragrance variants require a separate dosing specification and are included by replacing part of the recipe, rather than adding unexplained annual tonnage.

Item / wet-basis conditionAnnual engineering quantityOperating meaning
Accepted bentonite powder / 10% moisture20,444 tonnes100-tonne ground-floor stock allocation; controlled particle size and swelling properties
Dry starch / 10% moisture5,111 tonnes50% of the fresh tofu mix; binding performance established by trial
Prepared soybean fibre / 10% moisture5,111 tonnes50% of the fresh tofu mix; dry soy fibre / okara meal rather than fresh wet okara
Accepted fresh ingredients / total30,667 tonnesIllustrative moisture balance; procurement allowance for rejected deliveries is separate
Process water3,351 m³About 2,043 m³ to mineral forming and 1,308 m³ to tofu conditioning
Total incoming water3,514 m³Process water plus 113 m³ domestic use and 50 m³ occasional washing, rounded
Clean screening returns400 tonnes mineral; 200 tonnes tofuInternal recirculation; excluded from purchased ingredients and saleable annual output
Evaporated material water4,018 tonnesAbout 2,488 tonnes mineral and 1,530 tonnes tofu; all allocated to dryer duty for conservative sizing
Packed product20,000 tonnes mineral; 10,000 tonnes tofuBoth at 8% moisture in the design account; 30,000 tonnes total
Purchased natural gasApproximately 599,000 Nm³35.8 MJ/Nm³ lower heating value; 4 MJ useful heat/kg evaporated water; 75% overall fuel-to-process efficiency
ElectricityApproximately 0.83–1.03 million kWhStaged production loads, scheduled shared services and gas-heated dryers; no electric microwave duty
Fragrance variantsExcluded from the unscented base balanceDose by mass and supplier specification; replace an identified recipe fraction for each approved SKU

Rounded bentonite granules with a controlled water balance

  1. The bentonite litter wet granulation system starts with purchased powder at a reference 10% moisture. Specify the clay mineral profile, swelling performance, grit and agreed powder size before delivery; a starting target is at least 90% below 150 micrometres. Wet run-of-mine clay would need a separate preparation section and changes both heat demand and building requirements.
  2. Unload bulk bags through an enclosed ground-floor station with extraction and a magnet where appropriate. Meter the powder to a pre-wetting mixer before the disc. Avoid lifting dense clay to the top storey merely to obtain gravity flow. The bentonite granules making machine selection is a custom disc unit, with diameter, inclination and residence behaviour confirmed by agglomeration trials.
  3. The mineral design uses about 20,444 tonnes of accepted powder and 2,043 m³ of added water annually. Clean returns contribute another 400 tonnes at 8% moisture. Together they enter granulation and drying at about 18% moisture, or about 5,150 kg/h during effective production. Water spray control follows powder moisture and granule growth, rather than a fixed one-percent addition.
  4. Feed the wet granules continuously to the dedicated belt dryer. The reference evaporation duty is about 560 kg/h; specify a unit capable of 750 kg/h under the agreed inlet-air and product conditions. Use an initial drying-air trial window of 100–140°C, then establish belt loading and residence time from measured granule moisture and strength. Air temperature is distinct from product temperature.
  5. Cool continuously before final grading. Screen out material below 1 mm and above 4 mm to retain the 1–4 mm commercial grade; an intermediate 2 mm deck can split the retail grades. Clean fines return directly, while clean oversize requires controlled breaking before reuse. The design return allowance is 2% of net output, not a claim that every powder stream can be recovered.
  6. Discharge the mineral grade to its own dry buffer and packing system. At 4.5 T/H and a 5 kg net bag, the duty is 900 bags/h. Specify 15 sealed bags/min as a demonstrated working rate, including normal film changes and checks. A reference drum screen and mineral packing extraction limit loose dust reaching the sealing zone; seal quality and pack mass remain release checks.

Small-diameter tofu pellets without wet-okara preparation

  1. For 2 mm tofu litter pellet production, the fresh blend is a process example of 50% dry starch and 50% prepared soybean fibre by incoming mass. Both ingredients are taken at 10% moisture in the balance. The blend is a trial basis, not a finished commercial recipe; starch grade, fibre structure and clumping tests determine whether binder changes are needed.
  2. Keep accepted starch and dry soy fibre in enclosed, identified ground-floor stocks. Transfer weighed batches to the second-floor room through segregated handling. Wet okara commonly requires dewatering, drying and spoilage control before this point; it cannot replace dry fibre tonne for tonne. Start fibre trials with at least 90% below 1 mm. Compliant fines bypass the trim grinder; coarse fibre needs size reduction before mixing.
  3. Blend water into the full charge, including screened returns, to reach a reference 20% moisture before forming. A 500 kg wet batch contains about 218 kg starch, 218 kg fibre, 8 kg return and 56 kg water after rounding; the controller uses unrounded recipe weights. The unscented base avoids assuming a fragrance dilution ratio. Any later liquid addition is included in the water and recipe account.
  4. One cat litter pellet machine forms the conditioned blend through a 2 mm die. The MSZLH320 reference has a 37 kW main motor and must demonstrate the required recipe-specific wet throughput. Adjust die compression, roller setting and cutter length together; the product target is a 2 mm diameter with a 5–15 mm cut, rather than treating screen aperture as pellet diameter.
  5. The gas-heated cat litter belt drying route uses a separate indirect-heating air circuit for the tofu product. About 383 kg/h of material water is removed, against a 500 kg/h design evaporation duty. Begin trials around 70–90°C drying air and adjust loading and time to reach the moisture target without scorching. Cooling is continuous; a fixed two-hour microwave cycle is outside this configuration.
  6. Transfer the cooled pellets gently to the tofu screen and dedicated finished buffer. Size belts, chutes and drop heights for fragile small-diameter pellets, and keep the organic product away from mineral dust. The dry handling duty is specified at 3 T/H, above the 2.5 T/H saleable rate and its clean return flow. Verify moisture after cooling rather than relying on a hot-dryer reading.
  7. For cat litter retail bagging in Japan, the tofu line needs 500 five-kilogram bags per hour at its reference net output. Specify ten sealed bags per minute as the demonstrated working rate, leaving handling allowance above that requirement. Different pack weights or litre-based packs require a new pouch-volume and filling-speed check; nameplate bag counts alone do not establish the plant’s output.
  8. Collect clean tofu fines in a closed return loop. The balance allows 200 tonnes of dry return per year, equivalent to 2% of packed output; return material is metered into the total wet batch. Quarantine wet agglomerates, contaminated sweepings and suspect stored material. The reference fresh ingredient input is about 10,222 tonnes, with about 1,308 m³ of added water and 1,530 tonnes evaporated.
  • The process water account is about 3,351 m³/year. Add 112.5 m³ for fifteen employees at 25 litres per person on 300 operating days, plus a 50 m³ annual allowance for occasional collected washing: approximately 3,514 m³ incoming water in total. Dry vacuum cleaning is routine. Domestic sewage is 90 m³ and collected wash water is 40 m³ on the stated allowances; segregate solids before an approved discharge or removal route.
  • The reference connected electrical load is 302 kW, with a 500 kVA supply providing 425 kW at a 0.85 power factor. At effective line loads of 80–100 kW for mineral production and 95–115 kW for tofu production, plus 20–25 kW of shared services across 4,800 hours, annual use is approximately 0.83–1.03 million kWh. Confirm voltage, 50 or 60 Hz frequency, starting method and protection for the actual Japanese site.
  • Both dryers use pipeline natural gas through separate controlled heat sources. Total annual material-water evaporation is about 4,018 tonnes. At 4 MJ of useful process heat per kilogram of evaporated water and 75% overall efficiency, the fuel allowance is approximately 599,000 Nm³/year at a lower heating value of 35.8 MJ/Nm³. The combined installed burner input is 1.75 MW; specify the gas meter for that input and the actual supplied gas.

For a Japanese buyer, the commercial decision starts with the bag the retailer will accept. Net weight, volume declaration, dust after transport, storage stability and disposal instructions affect the required machinery. These checks connect the factory specification to an actual sales channel without relying on a national market-growth percentage or an assumed retail premium.

Weight volume and the chosen particle grade

The bentonite grade is screened to 1–4 mm, with finer dust and oversize handled separately. The tofu grade targets a 2 mm diameter and a 5–15 mm cut length. These are different handling products: mineral litter is denser, while plant pellets usually require more packaging volume for the same weight. Packing trials should therefore establish both mass rate and bag volume before pouch dimensions are ordered.

Transport samples before approving the product

Retail samples should travel through the intended distribution route before approval. Compare the fines before and after transport, check seals for powder contamination and assess how the bag stands on a shelf. The Japanese cat litter product trials should also compare clump integrity at a fixed liquid dose and waiting time. Use one written method across samples; attractive fresh pellets alone cannot establish performance in a customer’s litter tray.

Disposal wording follows the destination

A plant-based ingredient list does not establish flushability, compostability or a particular disposal category. Used mineral litter and tofu litter need instructions that match the destination municipality and the finished product. Japanese municipalities can prohibit toilet disposal even where a pack suggests it is possible. Confirm local guidance before artwork approval and avoid a universal flushing claim on this product range.

Resolve the building and utility interfaces early

Building reuse makes the machinery interface especially important. The review covers floor penetrations, fire compartments, combustible starch dust, gas-burner exhaust and the route for removing a ring die. These are project-specific design tasks for the supplier and local specialists. They should be settled before foundations and ducts are ordered, with the Japanese electrical supply and site frequency stated on the purchase specification.

A useful specification for this cat litter factory in Japan ends with acceptance conditions: saleable hourly output, incoming moisture, final moisture, particle grade and agreed bag size. The production test should run long enough to include stable drying and normal screening returns. RICHI can then connect process selection, machine supply, controls and commissioning to those conditions, giving the buyer a clear basis for comparing equipment proposals.

Five decisions before the equipment order

Fix the two finished products before choosing dies or screens. Supply a target bentonite size distribution and a tofu pellet sample, together with the preferred moisture and bag format. The bentonite and tofu litter manufacturing in Japan design keeps the mineral and plant grades separate through storage, forming and final packing. A blended retail product would need an additional controlled blending step.

Select machinery against wet load as well as final output. The bentonite route handles about 5,150 kg/h of wet granules; the tofu press handles about 2,933 kg/h of conditioned mixture. One appropriately sized machine meets each forming duty. On the tofu line, die trials establish whether the nominal 3–4 T/H MSZLH320 rating is achievable with the specified 2 mm product and the customer’s particular fibre.

Confirm the receiving door, goods lift and truck booking arrangements before approving the site. Raw bentonite travels a short, enclosed route from receiving to the ground-floor line. Starch and dry soybean fibre use a segregated transfer route to the second floor. Daily deliveries suit the limited heavy-stock area better than filling the upper storeys with bulk bags whose floor loads have not been approved.

Prepare a layout with maintenance envelopes as well as machine footprints. The design allows about 4–5 m of clear equipment height for the second-floor forming room and reserves a guarded down-feed route to its ground-floor dryer. Lift capacity, headroom and floor openings must match the heaviest removable component. Packing exits to dispatch without crossing open ingredient handling.

Plan six production staff per shift: one on each process route, two on packing, one for materials movement and one shift lead. Three shared posts cover quality coordination, maintenance and administration, giving fifteen employees overall. Automatic weighing and sealing are necessary for this staffing basis. Leave, specialist maintenance and peak dispatch support must be covered in the operating roster.

Keep the annual target within the operating calendar

Sequence both lines against dryer availability and finished-stock space. The mineral line needs about 4,444 effective hours, leaving roughly 356 scheduled hours for starts, cleaning and maintenance. The tofu line needs 4,000 hours and has 800 hours of calendar allowance. If mineral-line stoppages exceed that allowance, the annual target requires extra operating time or a proven increase in net output.

Set a provisional release specification of 8% moisture, with a working control band of 7–9%, and cool product to within 5°C of ambient before sealing. The bagged-product target for loose fines is no more than 1% under an agreed sieve method. Treat these as commissioning criteria to prove with the recipe, packaging and transport test, alongside absorbency, clump strength and microbiological checks for the plant-based grade.

The ground-floor raw-material allocation is 100 tonnes of bentonite and 30 tonnes each of starch and soybean fibre. That supports 1–2 days of mineral operation and less than two days of the tofu ingredients at the annual average. A 150-tonne finished-stock limit represents about one and a half average production days. Use booked deliveries, batch identification and humidity control to keep that compact buffer dependable.

Separate mineral dust collection from the starch-and-fibre system. Assess the combustible dust properties of the actual organic blend and specify protection, isolation and safe access accordingly. Guard the disc pelletizer and ring-die drive, monitor dryer temperature and airflow, and interlock gas firing with ventilation. The emergency-stop layout must cover both floors without relying on an operator running between rooms.

Use source extraction at bag opening, transfer points, screening and packing. Return only identified, clean material to its own recipe; spills, contaminated filter residues and rejected finished bags go through a separate disposition procedure. Vacuum cleaning is the normal method. Occasional washing has a collected-water route, while dryer exhaust and noise-control duties are established from the final airflows and local site conditions.

For cat litter machinery installation in Japan, RICHI can prepare the process diagram, equipment interfaces, electrical load schedule and commissioning sequence around the existing building. A shipment route from Qingdao to Yokohama is a planning option, with the receiving port chosen for the actual site. The final budget must define machinery, freight, import costs, local services, structural work, installation and opening stock separately.

Planning a cat litter factory in Japan? Send RICHI your bentonite analysis, fibre and starch samples, target bags and building drawings. We can check the two forming duties, dryer evaporation loads and installation access together, then prepare a scoped equipment proposal with the product tests needed before purchase.

Consultation and Definitions of 6-7T/H Cat Litter Factory In Japan
Design and Engineering of 6-7T/H Cat Litter Factory In Japan
Equipment Manufacturing of 6-7T/H Cat Litter Factory In Japan
equipment testing of 6-7T/H Cat Litter Factory In Japan
Equipment delivery of 6-7T/H Cat Litter Factory In Japan
install of 6-7T/H Cat Litter Factory In Japan
Operator Training of 6-7T/H Cat Litter Factory In Japan
6-7T/H Cat Litter Factory In Japan
 Workshop

Who we are

RICHI Machinery is one of the world’s leading suppliers of technology and services for the animal feed, aqua feed and pet food industries, also the largest pellet production line manufacturer in China.

Since 1995, RICHI’s vision to build a first-class enterprise, to foster first-class employees, and to make first-class contributions to society has never wavered.

In the past three decades, we have expanded our business to a wide range of areas, including animal feed mill equipment, aqua feed equipment, pet feed equipment, biomass pellet equipment, fertilizer equipment, cat litter equipment, municipal solid waste pellets equipment, etc.

Email email
WhatsApp whatsapp
Get Quote!

LEAVE YOUR NEEDS

Keeping in touch with us is an effective way to solve all your problems. If you have any needs or questions, please leave your contact information, then RICHI technical consultants will send design, quotation, videos to your mailbox. You can also contact us directly via WhatsApp: +86 138 3838 9622

    Application:

    * We will store the information you have provided us. We will only use this information for the purpose of helping to answer your inquiries. We will not disclose your information to third parties.

    +
    Scroll to Top