3–4 T/H biomass pellet processing line in Kyrgyzstan

Biomass Pellet Processing Line In Kyrgyzstan

This biomass pellet processing line in Kyrgyzstan was completed for a local agricultural processing enterprise. Its front section prepares and pelletizes woody and crop residues in the 3–4 T/H class. The downstream section turns part of those pellets into charcoal, with separate liquid recovery and process-gas heating.

The owner combined residues from its agricultural operations with material purchased from local growers and wood processors. Sawdust and suitable crop stalks formed the feedstock scope. Shells and husks were also accepted material types where available; their suitability depended on the delivered condition and intended fuel specification.

The annual programme comprised 2,000 tonnes of fuel pellets for direct dispatch and 3,000 tonnes of charcoal. Most of the pellets formed upstream therefore continued into carbonization. The press had to serve both streams, while the retorts had their own charging, heating and cooling cycle.

The biomass pellet plant used about 15,233 tonnes of incoming biomass per year as its material-planning basis. Incoming moisture was 35%, with a 10% target after low-temperature drying. These two moisture levels determine the prepared-feed quantity and the water removal required before pelletizing.

The customer funded the project from its own resources. Existing factory space accommodated preparation, pellet forming and the thermal section, together with raw-material and finished-product holding areas. Reusing that space was part of the project’s construction arrangement.

Seven staff supported the operation. The line calendar provided two six-hour shifts on each of 300 working days, equivalent to 3,600 scheduled hours annually. Productive pelletizing time and complete retort cycles were separate operating measures within that calendar.

pelletizing capacity

project investment

location

project type

The biomass pellet processing line in Kyrgyzstan occupied about 3,000 m² of existing factory space. The equipment arrangement comprised one main pellet press, an electric low-temperature dryer, five carbonization retorts and their connected transfer and gas-handling equipment.

The biomass pellet production line connected material receiving with drying and pellet forming before the product split. The charcoal route continued through the retorts and cooling section. Raw residues, accepted pellets, charcoal and recovered liquid fractions each had a defined holding function.

Workshop functionArrangementMaterial handled
Existing factory spaceAbout 3,000 m²Full project operation
Raw-material holdingNorthwest workshop cornerIncoming biomass residues
Preparation and formingConnected processing areasDried pellet feed
Thermal sectionFive carbonization retortsPellets for charcoal
Southern product holdingSeparate product routesPellets charcoal and liquids
Office facilitiesExisting provisionManagement and staff

Fuel pellets were the uncarbonized product. Their feed could include sawdust, suitable woody residues, straw and vegetable stalks, with shells and husks handled according to availability and product requirements. Material selection also affected the charcoal obtained from the second branch.

The two solid-product programmes totalled 5,000 tonnes annually. This finished-product total was different from the amount passing through the pellet press: feed intended for charcoal also had to be formed first. The condensate allowance belonged to the thermal section and was counted separately.

Product streamAnnual programmeRoute
Fuel pellets2,000 tonnesDirect product dispatch
Biomass charcoal3,000 tonnesRetorts then controlled cooling
Total solid products5,000 tonnesSeparate solid-product outlets
Liquid condensateAbout 2,995 tonnesCooling then fraction separation

Carbonization also released vapours and gas. Cooling that stream recovered liquid condensate containing aqueous and tar-rich fractions. The remaining combustible gas returned to the retort heating circuit when enough was available. Its flow depended on the stage of the thermal cycle.

Fuel pellets for direct dispatch

Crushed and dried biomass was compressed into fuel pellets. The direct-sale branch used the 10% moisture planning basis and the 2,000-tonne annual programme. Pellet dimensions, handling strength and fines acceptance followed the receiving fuel system; mixed agricultural residues were assessed for that application.

Charcoal from pelletized biomass

The second branch heated prepared pellets under oxygen-limited conditions in carbonization retorts. Thermal decomposition produced charcoal together with vapours and non-condensable gas. Charcoal remained a separate product from the uncarbonized pellets dispatched from the front section.

The charcoal programme was 3,000 tonnes annually. Feed composition, retort temperature and the heating cycle affected its yield and properties. Moisture, ash and residual volatile content needed to suit the intended buyer’s use, with product values established by testing the relevant batch.

Charcoal acceptance checks include:

  • Fuel properties: moisture, ash and volatile content against the purchase specification.
  • Handling condition: cooling, particle integrity and fines before storage or packing.
  • Batch identity: the biomass feed and thermal treatment behind the delivered product.

Condensate settling and liquid separation

The recovery circuit cooled the vapours leaving carbonization. The collected liquid was crude condensate rather than a distilled chemical product. Settling separated aqueous wood-vinegar and tar-rich fractions for their respective handling routes.

The liquid collection programme allowed about 2,995 tonnes annually. This was a planning quantity for the condensate stream, whose water and organic content followed feed condition and thermal operation. Product acceptance required the specification appropriate to the actual liquid fraction.

Recovered streamSeparation stepNext duty
CharcoalRetort discharge after coolingSolid-product holding
Crude condensateWater-cooled vapour recoveryLiquid receiver
Aqueous fractionSettling and withdrawalSeparate containers
Tar-rich fractionSettling and withdrawalSeparate liquid handling
Non-condensable gasAfter vapour condensationRetort heat circuit

The liquid receiver allowed settling before the separated fractions were transferred into suitable containers. Storage kept those fractions apart from solid fuel products. Condensate weight was a thermal-recovery quantity and was not added to the pellet press’s saleable solid output.

Liquid collection depended on gas cooling and the separation conditions in the receiver. A stable layer interface supported withdrawal of the intended fraction. The amount collected and its composition were distinct measures; neither followed from the raw-material name alone.

Recovered gas for retort heat

Gas remaining after condensation contained combustible components together with non-combustible components. It passed to the heating circuit serving the carbonization section. Available flow and fuel value changed through the cycle as the biomass heated and decomposed.

Bottled LPG provided startup heat. Recovered process gas then contributed indirect heating once the thermal section generated a usable supply. Startup fuel and recovered gas served different operating stages; the heat balance depended on the retort load and gas available at the time.

A main pellet press with five thermal retorts

The equipment schedule comprised 16 principal units or sets. One appropriately sized biomass press served the 3–4 T/H forming section. Five retorts handled the carbonization branch, with an electric dryer, a crusher and the transfer and collection systems completing the listed arrangement.

Packaging materials had an annual procurement allowance of 10 tonnes and arrived by road. They served the product-handling programme separately from the biomass feed account. The total did not establish a particular bag weight or number of filled packages.

EquipmentQuantityDuty
Biomass pellet press1Form prepared biomass
Electric low-temperature dryer1Remove water before forming
Feed and discharge screws5Transfer prepared material
Small crusher1Reduce suitable coarse residues
Thermal gas collection system1Recover retort vapours
Carbonization retorts5Convert pellets into charcoal
Particle collection equipment1Connected collection duty
Electrostatic collection unit1Thermal gas-system duty
Principal equipment total16Units and sets

Annual incoming material and drying balance

The drying calculation used 15,232.945 tonnes of incoming material at 35% moisture. With all dry solids retained, bringing that material to 10% moisture gives about 11,002 tonnes of prepared feed. The balance below uses wet-basis moisture and precedes handling losses.

Calculated annual flowApproximate quantityBasis
Incoming wet biomass15,233 tonnes35% moisture
Prepared feed11,002 tonnes10% moisture
Water removed4,231 tonnesDrying balance
Pellets for direct dispatch2,000 tonnesSolid-product programme
Prepared pellets for retorts9,002 tonnesBefore handling losses

After allocating 2,000 tonnes to direct pellet dispatch, about 9,002 tonnes remained for the charcoal route on the same calculation basis. A 3,000-tonne charcoal programme corresponds to roughly one third of that retort feed by gross weight. Actual conversion also depends on feed and thermal conditions.

Across the 3,600-hour scheduled year, the calculation averages about 3,056 kg/h of prepared feed and 1,175 kg/h of evaporation. These are annual-load averages. Dryer peak duty, productive press hours and retort turnover still follow their individual operating conditions.

Capacity measureCalculated figureMeaning
Scheduled operation3,600 hours/yearTwo six-hour shifts
Average prepared-feed demand3,056 kg/hAnnual feed over calendar
At 4 T/H formingAbout 2,751 hoursBefore forming losses
Average evaporation demand1,175 kg/hAnnual water over calendar

Purchased residues arrived by road and entered temporary raw-material storage. Receiving identified the material form and moisture before choosing the preparation route. Sawdust already within the feed specification avoided unnecessary crushing, while coarse stems and woody pieces needed size reduction.

The main sequence was receiving, particle preparation, electric drying and pellet forming. Accepted pellets then divided between dispatch and carbonization. The thermal branch continued through charcoal cooling and vapour condensation, with separated liquid collection and recovered gas supplying part of the retort heat.

Particle preparation for mixed residues

Coarse straw, vegetable stalks and suitable woody residues passed through the small crusher within its feed-size and loading limits. Shells and husks also needed a particle check; their material names alone did not establish that they could bypass size reduction.

The prepared particles entered the conveying screw. Collection at the preparation and transfer points supported the connected material-handling route. Material returned from collection had to remain suitable for the same feed specification before re-entering production.

Enclosed feed transfer

The feed inlet accepted suitably sized crushed material or incoming fines. Enclosed screw transfer moved this material toward the dryer. Feed continuity mattered because irregular delivery to the drying stage would also change the condition and quantity reaching the press.

Electric drying before pelletizing

The electric low-temperature dryer reduced the stated 35% incoming moisture toward the 10% preparation target. Drying controlled water removal before forming, while the particle-preparation step controlled size. Both conditions had to be suitable at the pellet-press inlet.

The biomass pellet making plant used an electrically heated drying stage with an operating temperature basis of about 60°C. A discharge screw transferred dried material to temporary holding before forming. Moisture at the dryer outlet governed release to the next stage.

Pellet forming and the product split

One biomass pellet press compressed the prepared feed into pellets. The 3–4 T/H class described this upstream forming duty, including pellets destined for the retorts. The direct-dispatch portion cooled to a suitable handling and storage condition before product release.

Carbonization in five retorts

The carbonization branch transferred pellets to five retorts. These units performed oxygen-limited thermal conversion, followed by charcoal cooling. The temperature bands below describe the heating stages; residence time followed the charge, heat transfer and required charcoal condition.

  • 60–150°C: warm the charge and remove remaining moisture during the initial heating stage.
  • 200–350°C: advance thermal decomposition as vapours and combustible gas develop.
  • 350–450°C: continue carbonization toward the required charcoal condition before cooling.

The annual material account kept charcoal, condensate, recovered gas and other process streams separate. Moisture released during heating formed part of the vapour stream. A fixed gas tonnage could not be derived from charcoal output alone because the feed and condensation conditions also mattered.

LPG supplied indirect startup heating. As carbonization developed a usable gas stream, the recovered fuel contributed to retort heating. The changeover followed gas availability and the heat demand of the operating charge.

After condensation, the remaining gas travelled through the recovery pipework to the retort heat circuit. The listed gas-collection and electrostatic equipment served the connected thermal system. Their functions were separate from the electric low-temperature dryer upstream.

Charcoal cooling and vapour condensation

Charcoal cooling and gas cooling were two different duties. The solid product needed to cool in a controlled condition before release from the thermal section. The vapour stream passed through water-cooled condensation to recover liquid into the receiver.

Settling in the liquid receiver separated the tar-rich and aqueous fractions. The container programme allowed up to 400 kg per barrel. Solid charcoal, liquid condensate and directly dispatched fuel pellets followed separate storage and dispatch routes.

The installation reused the existing factory building. Temporary raw-material storage occupied the northwest part of the workshop, and finished-product holding was on the south side. These positions connected road receiving with the internal process route and subsequent dispatch.

The workshop accommodated crushing, low-temperature drying, pellet forming, carbonization and cooling with liquid separation. The route followed the product split after forming. Pellet dispatch did not need to pass through the retort sequence, while charcoal required its complete thermal and cooling cycle.

Short internal transfers connected successive operations. Incoming residue movements, solid-product dispatch and liquid withdrawal each used their own handling arrangements. The existing office and staff facilities supported the workshop without a site canteen or dormitory.

Personnel water allowance

Municipal water served the seven-person operation. At the personnel allowance of 50 litres per person per working day, 300 days gives 105 m³ annually. This was staff water, separate from circulation through the gas-condensing equipment.

Condenser circulation and makeup

The condenser circulation basis was 2.8 m³/h. At a makeup allowance equal to 1% of that flow, the calculated addition was 28 litres per hour. Applying that allowance across the full 3,600-hour calendar gives 100.8 m³; actual addition follows condenser use and water loss.

Water dutyPlanning figureTime basis
Staff water105 m³/yearSeven staff and 300 days
Condenser circulation2.8 m³/hRecirculating flow
Makeup at 1%28 litres/hourWhile the loop operates
Full-calendar makeup calculation100.8 m³/year3,600 operating hours assumed

Electricity for preparation and forming

The existing local electricity connection served the electric dryer, main press and auxiliary drives. Dryer demand followed the water-removal duty as well as heat losses. Motor loading and operating time determined electrical consumption across the preparation and forming section.

Two distinct heat requirements

Low-temperature preparation used electric heat. Carbonization used indirect heating, starting with LPG and drawing on recovered process gas as the cycle developed. These were different heat duties within the complete plant.

The five retorts also needed time for loading and controlled cooling. Their annual charcoal capacity followed charge weight, complete cycle duration and conversion yield. Upstream pellet capacity therefore did not by itself establish the thermal section’s hourly or annual output.

Give existing residue streams a fuel outlet

The customer already handled agricultural residues through its growing and processing activities. Linking that resource with purchased sawdust created an identifiable feedstock base. Receiving and preparation turned suitable lots into press feed rather than treating every incoming residue as ready for forming.

Feed two products through one press

The biomass pellet mill served both product outlets. Direct fuel pellets left the front section, while the balance supplied the retorts. Keeping that split explicit connected raw-material preparation with each product programme and the corresponding storage requirement.

Match pellets to local heat equipment

Local heat users provided a market direction for the pellet branch. Fuel acceptance depended on the buyer’s burner, feeding arrangement and ash-handling provision. Crop-residue pellets were offered according to their material and fuel properties rather than a generic household wood-pellet claim.

Coordinate the press with retort cycles

Five retorts gave the thermal branch its own operating sequence. Charging, heat supply and cooling had to follow that sequence while the pellet section supplied prepared material. The production account connected press output, retort feed and accepted charcoal without counting the same pellets twice.

Handle each recovered product separately

Charcoal and recovered liquids added distinct handling tasks to the plant. Their collection, holding and dispatch were part of the workshop arrangement. The process-gas circuit also linked the thermal conversion stage with retort heat, making the full project broader than a fuel-pellet line alone.

For a biomass pellet processing line in Kyrgyzstan, discuss the residue types, incoming moisture and pellet specification with RICHI. A project supplying both pellet fuel and charcoal also needs a defined product split, retort cycle and liquid-recovery arrangement alongside the upstream forming capacity.

Consultation and Definitions
Complete Biomass Pellet Plant in Romania
Equipment Manufacturing
equipment testing
Equipment delivery
Operator Training
Wood Pellet PlantWorkshop

Who we are

RICHI Machinery is one of the world’s leading suppliers of technology and services for the animal feed, aqua feed and pet food industries, also the largest pellet production line manufacturer in China.

Since 1995, RICHI’s vision to build a first-class enterprise, to foster first-class employees, and to make first-class contributions to society has never wavered.

In the past three decades, we have expanded our business to a wide range of areas, including animal feed mill equipment, aqua feed equipment, pet feed equipment, biomass pellet equipment, fertilizer equipment, cat litter equipment, municipal solid waste pellets equipment, etc.

Email email
WhatsApp whatsapp
Get Quote!

LEAVE YOUR NEEDS

Keeping in touch with us is an effective way to solve all your problems. If you have any needs or questions, please leave your contact information, then RICHI technical consultants will send design, quotation, videos to your mailbox. You can also contact us directly via WhatsApp: +86 138 3838 9622

+
Scroll to Top