4–4.5 T/H dog food factory in Spain

4–4.5 T/H dog food factory in Spain

The buyer’s practical task was to establish a repeatable product specification and a reliable production route. The project record does not include a confirmed retail contract, subsidy agreement or market-share result. National turnover figures and forecasts are therefore not used to prove this factory’s sales or return on investment.

The planned pet food production line occupied a listed 17,589 m² site with 20,321.72 m² of gross building floor area. Multiple building levels explain why floor area exceeds land area. The investment figure shown below is the source total-project provision; the equipment subtotal is not added again as a second project investment.

The dog food factory in Spain uses a dry-ingredient route with measured conditioning, one pet food extruder machine, one pet food dryer, post-drying fat and palatant application, active cooling and retail packing. Its 20,000-tonne annual target is final accepted food, not the wet mass passing through the extruder.

The source headcount was 42 people, with a canteen and no dormitory. Two eight-hour equipment shifts on 300 days provide 4,800 scheduled hours. At 4 T/H even uninterrupted production yields only 19,200 tonnes, so the engineering reference uses 4.5 T/H accepted output and approximately 4,444 net hours, leaving about 356 hours for interruptions.

capacity

total project investment

location

project type

The dog food factory in Spain is sized around one product stream and a demanding annual operating calendar. The selected mass account uses 8% final moisture, powder ingredients at 10% water and explicitly defined post-dry coatings. These conditions require product and recipe trials rather than a simple conversion of the original equipment list into guaranteed output.

Product and operating basisReference quantityBoundary
Accepted dry dog food20,000 tonnes/yearAfter retained coating
Selected final running output4.5 T/HNot wet extruder feed
Scheduled equipment hours4,800300 days × 16 hours
Net productive requirementAbout 4,444 hours20,000 ÷ 4.5
Interruption allowanceAbout 356 hoursAbout 93% utilisation required
Final water8% wet basisNot a shelf-life result
Kibble size4–12 mm design enquiry rangeEach shape and recipe needs a capacity trial

The original annual ingredient schedule totals 20,000 tonnes, including 1,000 tonnes labelled mould inhibitor and 400 tonnes antioxidant. Those entries would equal 5% and 2% of final food respectively and cannot be used as generic additive doses. The reference below uses an approved powder blend as a mass category instead of treating those figures as a validated recipe.

Material categorySource annual entryEngineering reference
Corn wheat and protein ingredients14,000 tonnes combinedWithin approved powder blend
Dicalcium-phosphate entry600 tonnesInclusion requires nutritional validation
Mould-inhibitor entry1,000 tonnesNot accepted as a generic dose
Antioxidant entry400 tonnesNot accepted as a generic dose
Total powder blend16,000 tonnes including those entries18,000 tonnes at 10% water for sizing
Retained chicken fat2,000 tonnes2,000 tonnes; nominally water-free
Palatant paste2,000 tonnes400 tonnes at assumed 50% solids
Total food ingredients20,000 tonnes20,400 tonnes in reference account

The 18,000-tonne powder category includes the actual formula’s approved ingredients and accurately dosed additions; it is not a replacement nutritional recipe. The source meat-and-bone-meal and 600-tonne phosphate entries do not establish an acceptable calcium, phosphorus or ash specification. Actual doses must follow the approved formulation and product strengths.

The reference changes the unverified palatant provision to a 400-tonne sizing case rather than certifying a 2,000-tonne paste dose. At 50% water, this adds 200 tonnes of retained water after drying. A different paste moisture, fat moisture, retention loss or rejected product requires an updated mass and dryer account.

Annual external food-process accountTonnesReference condition
Powder ingredients18,00016,200 tonnes dry matter
Retained fat2,000Nominally water-free
Retained palatant400200 tonnes water and 200 tonnes dry matter
Direct process steam600Enters conditioning water
Liquid conditioning water3,377.73External process addition
Total external input24,377.73Before rounding
Accepted coated dog food20,00018,400 tonnes dry matter; 8% water
Assumed die-flash water400Calculation allowance
Main-dryer water removal3,977.73External evaporation
Total external output24,377.73Rounding closes

The account assumes no stock change, no net dry-matter loss and full retention of the stated coating quantities. Dried net core is 17,600 tonnes containing 16,200 tonnes of dry matter and 1,400 tonnes water, about 7.95% core moisture. Adding fat and paste then gives 20,000 tonnes with 1,600 tonnes water, or 8%.

Eligible uncoated-core return is assumed at 2% of net core: 352 tonnes, containing 324 tonnes dry matter and 28 tonnes water. At 26% gross wet-feed moisture, annual extruder feed is about 22,329.73 tonnes, or 5.02 T/H over the net calendar. Return is internal, not extra procurement or extra accepted output.

One twin-screw main machine covers the corrected wet-feed duty. A higher-power SPHS150×2 configuration with a 200 kW main drive and reference 5–6 T/H range is selected for approximately 5.02 T/H wet feed. This is an engineering selection rather than a checked delivery nameplate. Exact screw, die and power variants require the agreed equipment data sheet and material trial.

Drying heat and conditioning steam are separate services

Annual utility referenceQuantityCalculation boundary
Main-dryer water removalAbout 3,977.73 tonnesCore drying only
Dryer fuel inputAbout 15,910.92 GJ4 MJ/kg evaporation assumption
Direct conditioning steam600 tonnes30 kg per tonne final food
Steam generation with 10% allowance660 tonnesDirect process plus service provision
Steam-generator raw make-upAbout 715.58 m³3% blowdown; 95% treatment recovery
Liquid process waterAbout 3,377.73 m³Separate from steam make-up
Personnel/canteen water945 m³42 people × 75 litres × 300 days
Reference fresh water totalAbout 5,038.31 m³Cleaning and other demands additional

The reference dryer uses indirect gas-heated air, while a separate small gas steam generator serves conditioning. At 1,100 kg/hour evaporation and 4 MJ/kg fuel input, the dryer needs about 1.22 MW, within the 1.3 MW allowance. Process steam generation at the selected running rate is about 0.149 T/H; confirm stable operation and start-up demand for the 0.3 T/H planning generator.

At 2.5 GJ useful steam duty per tonne and 90% overall generator efficiency, steam fuel adds about 1,833 GJ/year. Combined dryer and steam fuel input is about 17,744 GJ/year, or approximately 496,000 Nm³ of gas at an assumed 35.8 MJ/Nm³. The normal-volume basis is 0°C and 101.325 kPa; actual gas quality and billing conditions need confirmation.

The source 900 m³ water allowance cannot cover the reference process addition alone. The 945 m³ personnel/canteen amount is a non-residential planning assumption, not measured use. Sanitary water, cleaning drainage, boiler blowdown and treatment rejects need identified handling; no automatic reuse or zero-discharge result is claimed.

Electrical load and energy budget

Connected-load allowancekWPlanning function
Twin-screw main drive200One selected configuration
Fine grinding160One main position
Main mixer22One working-batch machine
Conditioning drives22.5Matched train
Extruder thermal allowance40Barrel-heating provision
Dryer fans and drives75Gas heat separate
Coating package37One retained-liquid route
Active cooling22Product finishing
Grading7.5Defined screen duties
Conveying45Including protected building transfer
Dry extraction30Matched circuits
Packing11One completed-bag route
Compressed air15Service allowance
Steam-generator auxiliaries5.5Separate direct-steam service
Controls and lighting15Production allowance
Total connected load707.5Engineering schedule

At an assumed 520–620 kW average productive demand over about 4,444 hours, process electricity is approximately 2.31–2.76 million kWh/year before non-production and separately added building services. The source 3.6 million kWh is treated as a budget allowance, not an operating meter record.

A preliminary 1,000 kVA connection provides about 850 kW at 0.85 power factor. Existing connection capacity was not supplied. Large-motor starting, simultaneous loads, transfer equipment and separately added building services require an electrical study before adopting the supply allowance.

Selected engineering equipmentQuantityDuty or drive basis
Fine-grinding position1≥5 T/H agreed powder; 160 kW allowance
Main dry mixer11,000 kg working batch; 22 kW
Twin screw extruder1SPHS150×2 200 kW configuration; ≥5.5 T/H wet duty
Conditioning train1Measured water and steam; 22.5 kW allowance
mesh belt dryer1≥6 T/H wet feed; ≥1,100 kg/hour evaporation
Indirect gas hot-air system11.3 MW fuel-input allowance
Coating package1≥6 T/H complete-cycle duty; 37 kW allowance
Active cooler and grading1 matched route≥6 T/H product handling
Conditioning steam generator10.3 T/H steam planning rating
Retail packing1 line≥600 completed 10 kg bags/hour

Prepare a measured dry blend

One fine-grinding position prepares the agreed ingredients, with compliant powders bypassing it. Use a preliminary 0.4–0.6 mm particle trial target and check fibre and mineral distribution. One 1,000 kg working batch every five minutes gives 12 T/H including filling and discharge, above the approximate 4.13 T/H powder-plus-core-return load. Two serial grinding sections and multiple main mixers are not retained without a demonstrated need.

Extrude wet feed then dry the core

Condition with metered liquid water and process steam. The selected single extruder must demonstrate approximately 5.02 T/H wet feed while producing the agreed final shape and density. A smaller 3–4 T/H wet-feed configuration cannot meet that reference. Motor load, barrel conditions and residence behaviour require trials; no universal microbial-kill result is inferred from extrusion.

After the assumed die flash, the dryer receives about 4.93 T/H and removes approximately 895 kg/hour water. The 1,100 kg/hour selection also leaves capacity if the assumed flash is lower. Drying air, heat-transfer temperature and product temperature are separate measurements; establish actual settings from water removal and food-quality tests.

Apply retained liquids and cool before transfer

Grade uncoated cores before the controlled fat-and-palatant application. A 1,000 kg coating batch every ten minutes gives 6 T/H including transfer, covering the 4.5 T/H finished stream. Verify retained fat, paste distribution and uptake rather than assuming a scale dose all remains on the kibble. Coated rejects have their own disposition and are not automatically returned through extrusion.

Cool and grade through gentle transfers, then convey protected cooled product toward Factory 4 for packing. A preliminary cooling release within 5°C above ambient needs confirmation at actual air conditions. Final moisture and water activity include the paste water; no uncounted post-coating drying stage is assumed.

Factory 1 contains the main processing route, while Factory 4 is assigned to packaging and finished stock. Factories 2 and 3 are reserved in the source arrangement. Their areas are not described as installed production capacity or automatically available raw-material storage. The south entrance needs a receiving and dispatch plan against the actual building layout.

The building schedule distinguishes total floor area from footprint. Factory 1’s figures correspond to four equal floor plates and Factory 4’s to two; that arithmetic is not proof that platforms, bin reactions or upper-level equipment loads are structurally acceptable.

Building or land itemGross floor area m²Footprint m²
Factory 1: main process2,932.08733.02
Factory 2: reserved2,052.641,026.32
Factory 3: reserved6,167.203,083.60
Factory 4: packing and stock6,776.803,388.40
Communication room2929
Corridor7575
Office building2,289572.25
Total listed buildings20,321.728,907.59
Site area17,589Land boundary; not another building
Landscape area1,760Separate site allocation

The listed areas sum correctly. Floor area ratio is about 1.16 times, not 1.16%; building coverage is about 50.64% and landscaping about 10%. After building footprint and landscape, the arithmetic site balance is 6,921.41 m², before dividing it among roads, loading, setbacks and services. This is not all available storage or truck waiting space.

Factory 1’s multi-level arrangement needs verified machine reactions, bin point loads, lifting access and duct penetrations. Factory 4 needs suitable finished-food zoning and a protected connection. No detailed building height, platform load rating or transfer distance was provided, so neither structure nor route is presented as already validated.

Average finished dispatch is approximately 67 tonnes per working day, or about three loaded trips at an illustrative 25-tonne payload. Ingredient receipts average 68 tonnes per day before separate fuel and service deliveries. The southern access and reserved buildings must be coordinated against the actual traffic and product-release plan.

Commercial planning for this dog food factory in Spain starts with the actual dog-food specification, approved ingredient system, buyer format and available hours. The following checks concern measurable factory duties rather than national sales forecasts or an assumed share of global exports.

Annual hours and the limiting recipe

The annual target requires 4,444 productive hours at 4.5 T/H. At 90% utilisation of the original calendar, output is only 19,440 tonnes. To reach 20,000 tonnes at that utilisation requires approximately 4,938 scheduled hours, above the source 4,800 hours.

Verify the limiting recipe and kibble size through the full route, including drying, coating and packing. A wet extruder trial alone does not establish the final accepted rate, and nominal capacity does not create additional annual working time.

Nutrition and claims need product evidence

The ingredient schedule does not demonstrate a complete and balanced dog diet or justify the mineral inclusion. Nutrient composition, the intended life stage and actual additive product strengths require a competent formulation and supporting analyses. No natural, additive-free or functional-health claim is assigned simply from the plant design.

Bag formats and completed packing rate

A 10 kg planning bag needs 450 completed bags/hour at 4.5 T/H and two million bags for the annual programme. Select one route for at least 600 bags/hour through weighing, filling and sealing, and verify pallet handling. Different formats or extended product holds can change the finishing and storage duty.

Registration and investment boundaries

Animal-feed establishment and animal-by-product requirements in Spain are separate from machine purchase. Confirm the actual regional registration or approval route and supplier eligibility through the relevant authority. A generic EU-compliance statement does not prove that this factory, its materials or its products have been approved.

No confirmed subsidy or tax incentive was supplied for this project, so none is included in the investment case. The source total-project figure is a planning provision, not an audited final construction account or evidence that every later engineering change is already funded.

Supplier specifications and retained liquid

Secure ingredients by measured specification and usable dry matter. The source animal meal, phosphate and protein-powder descriptions require identity, nutrient and contaminant checks; a broad raw-material name is not a purchasing specification. The Spain dog-kibble palatant water allowance is especially important because the post-dry liquid becomes part of final food moisture.

The reference palatant dose and solids content are equipment-sizing assumptions, not a feeding recommendation or a claimed optimum flavour system. A wetter paste or larger dose can require lower core moisture or a separately designed finishing-drying step; it cannot be substituted without revising the account.

Product release needs measured moisture and water activity, relevant physical properties and the required food-safety evidence. Eight percent final moisture alone does not validate shelf life. Coating-liquid quality and clean post-heat handling are part of that release system.

The Spain multi-building kibble transfer plan must keep cooled product protected between processing and Factory 4. Use controlled transfers, traceable holding and achievable loading cycles. Reserved buildings and a large gross floor area do not establish hygienic routes, structural capacity or dispatch efficiency by themselves.

For a comparable dog food factory in Spain, provide the approved powder formula, ingredient moisture, retained coating dose, kibble size, bag format and operating calendar. These inputs allow the wet extrusion, core drying, post-coating water and factory-transfer duties to be matched before the final equipment and utility scope is agreed.

Consultation and Definitions
Design and Engineering
Equipment Manufacturing
equipment testing
Equipment delivery
Operator Training
Wood Pellet PlantWorkshop

Who we are

RICHI Machinery is one of the world’s leading suppliers of technology and services for the animal feed, aqua feed and pet food industries, also the largest pellet production line manufacturer in China.

Since 1995, RICHI’s vision to build a first-class enterprise, to foster first-class employees, and to make first-class contributions to society has never wavered.

In the past three decades, we have expanded our business to a wide range of areas, including animal feed mill equipment, aqua feed equipment, pet feed equipment, biomass pellet equipment, fertilizer equipment, cat litter equipment, municipal solid waste pellets equipment, etc.

Email email
WhatsApp whatsapp
Get Quote!

LEAVE YOUR NEEDS

Keeping in touch with us is an effective way to solve all your problems. If you have any needs or questions, please leave your contact information, then RICHI technical consultants will send design, quotation, videos to your mailbox. You can also contact us directly via WhatsApp: +86 138 3838 9622

    Application:

    * We will store the information you have provided us. We will only use this information for the purpose of helping to answer your inquiries. We will not disclose your information to third parties.

    +
    Scroll to Top