Recently, mixers, excavators, cranes… multiple equipment are operating at the same time at the construction site, and the machines are roaring. At the construction site of the 20-ton sheep cattle feed production line project, you can see that transportation vehicles are shuttled back and forth, and workers are working in an orderly manner, creating a busy scene.

The UAE ruminant feed mill project has officially started construction at the end of November 2023 and strives to be officially put into production in October 2024.

This ruminant sheep cattle feed mill equipment construction project has a total investment of US$1.4 million and covers an area of 1,200 square meters. The construction content includes main engineering, storage and transportation engineering, auxiliary engineering, and environmental protection engineering.

It mainly constructs feed production lines and production workshops, raw material warehouses, finished product warehouses, etc., and other supporting constructions affiliated facilities.

Entering the factory area, you can see that the steel structure on the first floor of Workshop 1 has been completed, the foundations of the raw material workshop and finished product workshop have been completed, the main structure of the comprehensive building has been completed, and decoration construction is in progress.

After the fully automatic cattle feed plant project is completed, it will reach an annual output of 100,000 tons of biological compound feed, provide employment for more than 40 people, effectively promote the development of local upstream and downstream industries such as livestock breeding, transportation, and packaging materials, and promote the healthy development of the local economy.